SLOATSBURG RT 17 ROAD CONSTRUCTION SCHEDULE
Posted on: July 12, 2021 - 6:27pm
Award of Contract - 03/06/2020
Original Contract Completion Date - 11/23/2021
Estimated Substantial Completion Date - 10/24/2021
Award of Contract - 03/06/2020
Original Contract Completion Date - 11/23/2021
Estimated Substantial Completion Date - 10/24/2021